Projects
Our client, Persimmon Homes will be opening the final section of our Phase 5 project at Hampton Park in Littlehampton West Sussex on Saturday 20th July.
The Bebo Arch Bridge structure in the wetlands area of the site has a span of approximately 14m from foundation to foundation, these being CFA piles with reinforced concrete pile caps. The structure is approximately 35m wide perpendicular to the span of the arch to accommodate the carriageway, shared cycleway / footway and associated verges and embankments.
Works are now complete for a new S278 junction at the Great Haddon development in Yaxley/Norman Cross for 1499 new homes. Works started last Summer and included initial vegetation clearance, earthworks fill operation, foul and storm drainage installation, installation of new utilities to feed the development, new traffic signals and street lighting, diversions of existing services (including a 12” Asbestos Water Main), carriageway construction works and surfacing.