We’re proud to have successfully delivered and opened the Friday Street and Yoxford roundabouts on the A12, on behalf of Sizewell C.
Delivered by our Suffolk-based team, these schemes are a testament to the hard work and dedication of everyone involved. Working across day and night shifts, our teams have ensured both projects were completed safely and efficiently.
These improvements will enhance access and significantly improve safety at key junctions along the A12, supporting connectivity to Sizewell C and benefiting local communities for years to come.
A huge thank you to our teams and partners who made this possible.
Across the two sites, we delivered:
• 15,500 m2 of base, binder and surface course asphalt laid
• 37,000 cubic metres of material excavated, moved and placed
• 2000 metres of drainage installed