HAMPTON PARK, LITTLEHAMPTON WEST SUSSEX

Our client, Persimmon Homes will be opening the final section of our  Phase 5 project at Hampton Park in Littlehampton West Sussex on Saturday 20th July.

The Bebo Arch Bridge structure in the wetlands area of the site has a span of approximately 14m from foundation to foundation, these being CFA piles with reinforced concrete pile caps. The structure is approximately 35m wide perpendicular to the span of the arch to accommodate the carriageway, shared cycleway / footway and associated verges and embankments.

The precast arch is assembled in segments and stitched together using reinforced concrete at the apex.

The reinforced embankments utilising lightweight Leca fill to reduce the loading on the sub-structure. 

A challenging project with some testing conditions has been delivered well by our site team of Trevor Bailey, Mick Murphy, Gary Stewart and Mark Enderby.