Development Infrastructure
21st February 2024 | 1 min read | admin
Lincoln Western Growth Corridor Phase 1a Update – We are working for Lindum Group on building a new road and bridge over the Catchwater with CFA piling works on the northern side of the brook and main bridge abutment and wingwall structures being constructed on the southern side. Works are progressing on the S38 and S278 highways works.
Piling fully has been completed with the north side fully cropped ready for abutment and wingwall works to commence. The bridge beams are due to be placed on 7th March with S278 widening works ongoing with night works commencing in 5 weeks’ time to complete the junction in full.
Breheny Civil Engineering