Installation of the main bridge beams over the A45 Eastern Green, Coventry took place on Friday and over the weekend. Nusteel Structures Limited and Ainscough Crane Hire lifted the 2x 80 tonne braced pair beams into place using a 550T lattice boom crane. The A45 dual carriageway, below the new bridge was opened 12 hours early, on Sunday evening.