We have recently completed our first phase of works at Angmering in West Sussex for Cala Homes. A dedicated bus link to serve the development alongside construction of the new main access and widening to the adjacent carriageway are now built. The site team, led by Miguel Alonso should be returning early in the new year to complete the project. This return visit will include a new roundabout on the A280 alongside associated embankment works.

We have also installed sheet piling, box culverts and insitu headwalls acting as preliminary work enabling widening of the existing junction of the A280 and Water Lane.